EXO Energy

How many solar installs has EXO Energy done in California, and which license number is on its installs?

EXO Energy has 4,687 residential solar installs interconnected in California, active in the records from 2020 through 2026 (Jul 13, 2020 to Aug 31, 2026), most of them in Riverside County (1,081), San Diego County (1,001) and San Bernardino County (719). CSLB lists license 1063308 (EXO ENERGY INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Feb 29, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
4,687
Last 24 months
1,340
Total capacity
40,771.6 kW DC
Median system size
8.1 kW DC
With battery storage
34.2% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 88.6% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
92.0% of 4,687 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
1,870 installs, latest Aug 31, 2026
Ownership types recorded
PPA 1,679, lease 265, prepaid lease 2, other 2,368
Median battery size
5 kWh (937 installs list a capacity)
First install
Jul 13, 2020
Latest install
Aug 31, 2026
Counties
45
Utilities
SCE 2,696, SDGE 1,068, PGE 923
CSLB license
1063308

Is EXO Energy still installing solar in California? Its latest install and its count in each month from September 2025 through August 2026 (547 in all).

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2020 to 2026

YearInstalls interconnectedWith battery storage
202080
20213850
20229802
20231,24920
20241,069374
2025693592
2026 (through Aug 31, 2026)303249

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

1,870 of its 4,687 interconnected installs (39.9% of the 4,686 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 68.8% of those on PG&E and SCE records include battery storage. The latest Net Billing Tariff install was approved Aug 31, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.030.1%not counted
NEM 2.02,81360.0%45 (2.4%)
Net Billing Tariff1,87039.9%1,190 (68.8%)
Not recorded1

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 4,314 of EXO Energy’s installs the utility recorded a third-party ownership type: PPA 1,679, lease 265, prepaid lease 2, other 2,368. Across all installers, 1,495 residential systems list a third-party owner name that matches EXO Energy exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Sunnova1,643
EXO ENERGY INC1,495
Enfin452
Lightreach195
Mosaic168

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 1,226 of EXO Energy’s 1,340 installs name a module maker in the “Generator Manufacturer” fields, and most of those (713, 58.2%) used modules recorded as Qcells.

In the last 24 months, 1,340 of EXO Energy’s 1,340 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (1,216, 90.7%) used inverters recorded as Enphase.

In the last 24 months, 1,031 of EXO Energy’s 1,340 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (900, 87.3%) used batteries recorded as Enphase.

1,161 of 1,237 battery-paired PG&E and SCE installs (93.9%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells7132,416
VSUN (Vietnam Sunergy)373911
SEG Solar182182
LONGi115466
Canadian Solar87163
Inverter makerEnphase1,2163,651
SolarEdge3991,340
Tesla131202
ABB56162
SMA40not in top list
Battery makerEnphase9001,006
Tesla115131
SolarEdge1919
FranklinWH33
LG314

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 3,894 of 4,687 installs, inverters on 4,687. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names EXO Energy as developer on 293 battery storage projects and as installer on 293 (293 name it as both), 293 projects in all with 8,748 kWh of storage. 161 have the status Paid, with $4,439,708 in current incentive allocations. Applications were received from Nov 15, 2023 to Mar 2, 2026.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid1615,186$4,439,708
Reserved541,548$1,398,020
Waitlist6127$112,604
Cancelled721,887$1,737,342

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency1563,850$3,670,99966$1,542,476
Residential Storage Equity1304,756$3,887,57295$2,897,232
Residential Solar and Storage Equity - AB 209 Non-POU7142$129,1040$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1063308EXO ENERGY INC (Corporation)CLEARC-10 Electrical ContractorFeb 13, 2020Feb 29, 20284,684

License numbers are the ones the utilities recorded on the interconnection applications (4,685 of 4,687 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1063308. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list EXO Energy’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2020202120222023202420252026Total
City and County of San Francisco106330800010001
unincorporated San Diego County1063308191671598526106472
unincorporated Marin County106330801000001

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Counties

CountyInstalls
Riverside1,081
San Diego1,001
San Bernardino719
Los Angeles452
Kern261
Orange223
Fresno197
Tulare142
San Joaquin69
Placer61
Santa Cruz54
Contra Costa45
Santa Clara40
Kings33
Merced31
Ventura25
Alameda24
Madera22
Solano20
Butte17
San Benito17
Yuba17
Yolo15
Monterey14
Sonoma13
El Dorado10
Sutter10
Nevada8
Marin7
San Mateo7
Stanislaus7
Calaveras6
Mendocino6
Santa Barbara5
Tehama5
Humboldt4
Lake4
San Luis Obispo4
Tuolumne3
Amador2
Glenn2
Napa1
Sacramento1
San Francisco1
Shasta1

Top cities

CityInstalls
San Diego214
Fresno137
Victorville124
Cathedral City110
Bakersfield107
Murrieta99
Chula Vista97
Moreno Valley97
Escondido85
Hesperia85
El Cajon83
Hemet81
Oceanside76
Perris74
Vista71

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
EXO ENERGY INC3,616
EXO Energy1,070
EXO ENERGY1

Common questions

Where does EXO Energy install solar?

Its installs are spread across 45 counties. The most are in Riverside County (1,081 installs), followed by San Diego County (1,001).

How often does EXO Energy install batteries with solar?

34.2% of its interconnected solar installs include battery storage across all years, and 88.6% in the last 24 months (1,092 of 1,232). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many EXO Energy installs are under NEM 3.0 (the Net Billing Tariff)?

1,870 of its 4,687 interconnected installs (39.9% of the 4,686 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 68.8% of those on PG&E and SCE records include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.