Solar City

How many solar installs has Solar City done in California, and which license number is on its installs?

Solar City has 697 residential solar installs interconnected in California, active in the records from 2006 through 2019 (Nov 20, 2006 to May 22, 2019), most of them in Santa Clara County (195), Fresno County (95) and San Mateo County (91). CSLB lists license 888104 (TESLA ENERGY OPERATIONS INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-39, C-46, expires Dec 31, 2026.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
697
Last 24 months
0
Total capacity
3,387.1 kW DC
Median system size
4 kW DC
With battery storage
0.7% all time; no installs in the last 24 months last 24 months
Third-party owned
6.8% of 695 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 21, lease 21, other 5
First install
Nov 20, 2006
Latest install
May 22, 2019
Counties
35
Utilities
PGE 687, SCE 10
CSLB license
888104

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2006 to 2026

YearInstalls interconnectedWith battery storage
200610
20071630
20081780
20091770
2010260
2011230
2012150
2013420
201480
201550
201600
2017501
201883
201911
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 697 interconnected installs with a tariff recorded (697) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.063891.5%not counted
NEM 2.0598.5%5 (8.5%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 47 of Solar City’s installs the utility recorded a third-party ownership type: PPA 21, lease 21, prepaid lease 0, other 5. Across all installers, 1,191 residential systems list a third-party owner name that matches Solar City exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Solar City29
SolarCity8
Tomorrow Comes Today, LLC2
USB SolarCity Owner IV, LLC2
AU Solar 1, LLC1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 676 of Solar City’s 697 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (167, 24.7%) used modules recorded as BP Solar.

Across all years, 696 of Solar City’s 697 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (327, 47.0%) used inverters recorded as Xantrex Technology Inc..

Across all years, 5 of Solar City’s 697 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (5, 100.0%) used batteries recorded as Tesla.

5 of 5 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerBP Solar0167
Kyocera0133
Evergreen Solar0131
Sanyo055
First Solar047
Inverter makerXantrex Technology Inc.0327
Fronius0242
Power-One047
ABB029
SolarEdge024
Battery makerTesla05

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 676 of 697 installs, inverters on 696. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Solar City as developer on 0 battery storage projects and as installer on 57 (0 name it as both), 57 projects in all with 698 kWh of storage. 54 have the status Paid, with $569,040 in current incentive allocations. Applications were received from Nov 22, 2011 to Feb 5, 2018.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid54648$569,040
Cancelled350$32,560

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage11238$90,1609$69,600
Not stated46460$511,44045$499,440

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
888104TESLA ENERGY OPERATIONS INC (Corporation)CLEAR, Class Removal PendingB General Building Contractor; C-10 Electrical Contractor; C-39 Roofing Contractor; C-46 Solar ContractorDec 7, 2006Dec 31, 202655

License numbers are the ones the utilities recorded on the interconnection applications (63 of 697 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The License Master file lists a pending classification removal date of Dec 30, 2026 for license 888104. A pending date is CSLB’s scheduled action if the underlying requirement is not met; it is not a finding of wrongdoing.

What a disciplinary bond is: CSLB’s Bond Basics page says that when a license has been revoked, or in some instances suspended, for a violation of the Contractors State License Law, the contractor must file a disciplinary bond with the Registrar to reinstate, reissue or reapply for a license, and that the bond must stay on file for at least two years (CSLB Bond Basics). The file gives one disciplinary bond entry per license and does not say which of those circumstances applied, what the case was about or how it ended. CSLB’s license detail page shows any public disciplinary action.

Local solar permits naming its license

Solar permits in city and county open data that list Solar City’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense201820192020202120222023202420252026Total
City and County of San Francisco888104126921341027960403524692
unincorporated San Diego County8881043693224094252672036982522,198
unincorporated Marin County888104617715911000221412

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Santa Clara195
Fresno95
San Mateo91
Alameda66
San Francisco61
Contra Costa35
Kern31
Placer14
Madera11
San Joaquin10
Marin9
Yolo7
El Dorado6
Merced6
San Luis Obispo6
Solano6
Butte5
Sonoma5
Napa4
Orange4
Kings3
Los Angeles3
Monterey3
San Bernardino3
Santa Cruz3
Stanislaus3
Sutter3
Shasta2
Calaveras1
Lake1
Mariposa1
Mendocino1
Nevada1
Sacramento1
Yuba1

Top cities

CityInstalls
Mountain View73
San Francisco61
Fresno53
San Jose53
Clovis35
Bakersfield31
Menlo Park19
Oakland18
Woodside15
Los Altos14
Berkeley13
Stanford13
San Carlos11
Fremont10
Atherton9

Names as recorded by the utilities

The utilities recorded this installer under 10 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Solar City601
Solar City Corporation65
SOLAR CITY11
Solar City Corp11
Solar City DBA Tesla3
SOLAR CITY CORPORATION2
solar city1
Solar city1
Solar CIty1
Solar CIty DBA Tesla1

Common questions

Where does Solar City install solar?

Its installs are spread across 35 counties. The most are in Santa Clara County (195 installs), followed by Fresno County (95).

How often does Solar City install batteries with solar?

0.7% of its interconnected solar installs include battery storage across all years.

How many Solar City installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 697 interconnected installs with a tariff recorded (697) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.