How many solar installs has Solar Home done in California, and which license number is on its installs?
Solar Home has 230 residential solar installs interconnected in California, active in the records from 2011 through 2016 (Dec 27, 2011 to Nov 22, 2016), most of them in San Diego County (54), San Bernardino County (53) and Los Angeles County (32). The license number recorded on most of its installs, 985474, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 230
- Last 24 months
- 0
- Total capacity
- 1,427.1 kW DC
- Median system size
- 5.7 kW DC
- With battery storage
- 0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
- Third-party owned
- 0.0% of 137 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- none recorded
- First install
- Dec 27, 2011
- Latest install
- Nov 22, 2016
- Counties
- 23
- Utilities
- SCE 139, SDGE 71, PGE 20
- CSLB license
- 985474
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2011 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2011 | 2 | 0 |
| 2012 | 24 | 0 |
| 2013 | 47 | 0 |
| 2014 | 88 | 0 |
| 2015 | 47 | 0 |
| 2016 | 22 | 0 |
| 2017 | 0 | 0 |
| 2018 | 0 | 0 |
| 2019 | 0 | 0 |
| 2020 | 0 | 0 |
| 2021 | 0 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 230 interconnected installs with a tariff recorded (230) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 226 | 98.3% | not counted |
| NEM 2.0 | 4 | 1.7% | not recorded |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on Solar Home’s installs. No residential system in the file lists a third-party owner name that matches Solar Home exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 97 of Solar Home’s 230 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (22, 22.7%) used modules recorded as Mitsubishi Electric.
Across all years, 228 of Solar Home’s 230 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (197, 86.4%) used inverters recorded as SolarEdge.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Mitsubishi Electric | 0 | 22 |
| Sunpreme | 0 | 13 | |
| American Solar Wholesale | 0 | 12 | |
| Silevo | 0 | 12 | |
| Renesola America | 0 | 7 | |
| Inverter maker | SolarEdge | 0 | 197 |
| SMA | 0 | 22 | |
| Enphase | 0 | 4 | |
| Schneider Electric | 0 | 4 | |
| Xantrex Technology Inc. | 0 | 2 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 97 of 230 installs, inverters on 228. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 985474 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 100 | ||||
License numbers are the ones the utilities recorded on the interconnection applications (109 of 230 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
Other names reported under the same license
- Solar Holmes: 103 installs, license 985474
Counties
Top cities
| City | Installs |
|---|---|
| San Diego | 13 |
| Apple Valley | 12 |
| Victorville | 12 |
| Borrego Springs | 10 |
| Escondido | 8 |
| Ridgecrest | 8 |
| Agoura Hills | 6 |
| Corona | 6 |
| Poway | 6 |
| Chula Vista | 4 |
| El Cajon | 4 |
| Lancaster | 4 |
| Moreno Valley | 4 |
| Bakersfield | 3 |
| Barstow | 3 |
Names as recorded by the utilities
The utilities recorded this installer under 6 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| SOLAR HOME INC | 94 |
| Solar Home | 78 |
| SOLAR HOME | 40 |
| Solar Home Inc | 14 |
| Solar Home, Inc | 3 |
| SOLAR HOME INC. | 1 |
Common questions
Where does Solar Home install solar?
Its installs are spread across 23 counties. The most are in San Diego County (54 installs), followed by San Bernardino County (53).
How often does Solar Home install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many Solar Home installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 230 interconnected installs with a tariff recorded (230) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors