Eagle Solar

How many solar installs has Eagle Solar done in California, and which license number is on its installs?

Eagle Solar has 64 residential solar installs interconnected in California, active in the records from 2009 through 2014 (Sep 8, 2009 to Nov 12, 2014), most of them in Los Angeles County (9), Santa Clara County (9) and Fresno County (8). The utilities did not record a CSLB license number on enough of these installs to look one up.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
64
Last 24 months
0
Total capacity
271.9 kW DC
Median system size
4.1 kW DC
With battery storage
0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 38 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
First install
Sep 8, 2009
Latest install
Nov 12, 2014
Counties
16
Utilities
PGE 38, SCE 22, SDGE 4
CSLB license
none reported

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2009 to 2026

YearInstalls interconnectedWith battery storage
200910
201010
2011230
2012210
2013130
201450
201500
201600
201700
201800
201900
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 64 interconnected installs with a tariff recorded (64) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.064100.0%not counted
NEM 2.000.0%0
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Eagle Solar’s installs. No residential system in the file lists a third-party owner name that matches Eagle Solar exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 42 of Eagle Solar’s 64 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (20, 47.6%) used modules recorded as Suntech.

Across all years, 63 of Eagle Solar’s 64 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (39, 61.9%) used inverters recorded as PV Powered.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSuntech020
BIPV013
Canadian Solar06
Qcells02
Trina Solar01
Inverter makerPV Powered039
Advanced Energy, Inc.019
SMA04
Open Energy Corporation01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 42 of 64 installs, inverters on 63. See the methodology and the equipment index.

Contractor license

The utilities did not record a license number for enough of these installs to look one up.

License numbers are the ones the utilities recorded on the interconnection applications (3 of 64 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it.

Counties

CountyInstalls
Los Angeles9
Santa Clara9
Fresno8
Tulare7
Yolo5
Kern4
Placer4
Contra Costa3
El Dorado3
San Diego3
Alameda2
Kings2
Orange2
Colusa1
San Bernardino1
Ventura1

Top cities

CityInstalls
Arcadia8
San Jose7
Fresno6
Tulare6
Davis4
Bakersfield3
El Dorado Hills3
Clovis2
Hanford2
Rocklin2
Apple Valley1
Auburn1
Bonita1
Caliente1
Clarksburg1

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Eagle Solar40
EAGLE SOLAR24

Common questions

Where does Eagle Solar install solar?

Its installs are spread across 16 counties. The most are in Los Angeles County (9 installs), followed by Santa Clara County (9).

How often does Eagle Solar install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many Eagle Solar installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 64 interconnected installs with a tariff recorded (64) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.