Sol Nova LLC
How many solar installs has Sol Nova LLC done in California, and which license number is on its installs?
Sol Nova LLC has 592 residential solar installs interconnected in California, active in the records from 2019 through 2025 (Jul 24, 2019 to Oct 30, 2025), most of them in San Diego County (567), Orange County (24) and Riverside County (1). The license number recorded on most of its installs, 1060203, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped. CSLB lists license 1000555 (BURKE ELECTRIC INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Jan 31, 2027, recorded on 235 of its installs.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
The installs credited to Sol Nova LLC here carry more than one CSLB license number: 1060203 on 341 (not found in the CSLB License Master file), 1000555 on 235 (CSLB holder BURKE ELECTRIC INC, Riverside) and 961988 on 13 (CSLB holder SUNPOWER, Orem), in the License Master file pulled Nov 4, 2026. They are grouped under one installer by the name written on the applications; the records do not say whether these numbers belong to the same legal entity.
- Interconnected installs
- 592
- Last 24 months
- 27
- Total capacity
- 3,267.8 kW DC
- Median system size
- 4.8 kW DC
- With battery storage
- 0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; not recorded (SDG&E files batteries as separate projects, not on the solar record) last 24 months
- Third-party owned
- 44.6% of 592 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 35 installs, latest Oct 30, 2025
- Ownership types recorded
- PPA 260, lease 4
- First install
- Jul 24, 2019
- Latest install
- Oct 30, 2025
- Counties
- 3
- Utilities
- SDGE 591, SCE 1
- CSLB license
- 1060203, 1000555, 961988
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2019 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2019 | 52 | 0 |
| 2020 | 142 | 0 |
| 2021 | 107 | 0 |
| 2022 | 183 | 0 |
| 2023 | 66 | 0 |
| 2024 | 25 | 0 |
| 2025 | 17 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
35 of its 592 interconnected installs (5.9% of the 592 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest Net Billing Tariff install was approved Oct 30, 2025.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 0 | 0.0% | not counted |
| NEM 2.0 | 557 | 94.1% | 0 (0.0%) |
| Net Billing Tariff | 35 | 5.9% | not recorded |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
On 264 of Sol Nova LLC’s installs the utility recorded a third-party ownership type: PPA 260, lease 4, prepaid lease 0, other 0. Across all installers, 9 residential systems list a third-party owner name that matches Sol Nova LLC exactly (after removing case, punctuation and suffixes such as Inc or LLC).
| Third-party owner named on its installs | Installs |
|---|---|
| SunRun | 113 |
| Sunnova | 76 |
| SolNova LLC | 55 |
| Sol Nova LLC | 9 |
| Everbright | 2 |
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 21 of Sol Nova LLC’s 27 installs name a module maker in the “Generator Manufacturer” fields, and most of those (12, 57.1%) used modules recorded as Mission Solar.
In the last 24 months, 27 of Sol Nova LLC’s 27 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (18, 66.7%) used inverters recorded as DuracellInc..
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Mission Solar | 12 | 23 |
| HyperionSolar | 6 | not in top list | |
| Canadian Solar | 2 | 156 | |
| UnitedRenewableEnergyCo.,Ltd. | 1 | 33 | |
| Inverter maker | DuracellInc. | 18 | 18 |
| Enphase | 9 | 210 | |
| SunPower | 2 | 5 | |
| ABB | 1 | 4 | |
| Power-One | 1 | not in top list |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 556 of 592 installs, inverters on 592. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 1060203 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 341 | ||||
| 1000555 | BURKE ELECTRIC INC (Corporation) | CLEAR | C-10 Electrical Contractor | Jan 26, 2015 | Jan 31, 2027 | 235 |
| 961988 | SUNPOWER (Corporation) | CLEAR, Pending Case/CIT | C-10 Electrical Contractor; C-46 Solar Contractor | Jun 10, 2011 | Oct 31, 2027 | 13 |
License numbers are the ones the utilities recorded on the interconnection applications (592 of 592 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for licenses 1000555, 961988. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Local solar permits naming its license
Solar permits in city and county open data that list Sol Nova LLC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.
| Permit data | License | 2021 | 2022 | 2023 | 2024 | Total |
|---|---|---|---|---|---|---|
| City and County of San Francisco | 1060203 | 0 | 0 | 4 | 0 | 4 |
| unincorporated San Diego County | 1060203 | 14 | 5 | 14 | 6 | 39 |
Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.
Other names reported under the same license
- SOL NOVA ELECTRIC LLC: 1,078 installs, license 1060203
- Burke Electric: 1,431 installs, license 1000555
- SunPower: 119,561 installs, license 961988
- Complete Solar: 13,319 installs, license 961988
- Complete Solar Solution of California In: 304 installs, license 961988
- COMPLETE SOLAR SOLUTION OF CALIFORNIA INC: 68 installs, license 961988
Counties
Top cities
| City | Installs |
|---|---|
| San Diego | 171 |
| Escondido | 78 |
| San Marcos | 51 |
| El Cajon | 50 |
| Chula Vista | 42 |
| Spring Valley | 34 |
| Lakeside | 19 |
| Oceanside | 18 |
| Santee | 18 |
| Fallbrook | 16 |
| Ramona | 15 |
| National City | 11 |
| Vista | 11 |
| Lemon Grove | 8 |
| La Mesa | 7 |
Names as recorded by the utilities
The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Sol Nova LLC | 591 |
| Sol Nova | 1 |
Common questions
Where does Sol Nova LLC install solar?
Its installs are spread across 3 counties. The most are in San Diego County (567 installs), followed by Orange County (24).
How often does Sol Nova LLC install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many Sol Nova LLC installs are under NEM 3.0 (the Net Billing Tariff)?
35 of its 592 interconnected installs (5.9% of the 592 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.