How many solar installs has LLUMETEC done in California, and which license number is on its installs?

LLUMETEC has 77 residential solar installs interconnected in California, active in the records from 2019 through 2021 (Oct 14, 2019 to Jul 30, 2021), most of them in Santa Clara County (32), Alameda County (18) and Contra Costa County (11). The license number recorded on most of its installs, 1029503, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
77
Last 24 months
0
Total capacity
413.6 kW DC
Median system size
4.9 kW DC
With battery storage
6.5% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 77 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
Median battery size
10.3 kWh (2 installs list a capacity)
First install
Oct 14, 2019
Latest install
Jul 30, 2021
Counties
14
Utilities
PGE 75, SCE 2
CSLB license
1029503

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2019 to 2026

YearInstalls interconnectedWith battery storage
201930
2020404
2021341
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 77 interconnected installs with a tariff recorded (77) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.077100.0%5 (6.5%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on LLUMETEC’s installs. No residential system in the file lists a third-party owner name that matches LLUMETEC exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 74 of LLUMETEC’s 77 installs name a module maker in the “Generator Manufacturer” fields, and most of those (59, 79.7%) used modules recorded as Canadian Solar.

Across all years, 77 of LLUMETEC’s 77 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (42, 54.5%) used inverters recorded as SolarEdge.

Across all years, 1 of LLUMETEC’s 77 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as LG.

1 of 5 battery-paired PG&E and SCE installs (20.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerCanadian Solar059
LG012
Evolve01
JinkoSolar01
Silfab01
Inverter makerSolarEdge042
Enphase034
SunPower01
Battery makerLG01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 74 of 77 installs, inverters on 77. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1029503Not found in the CSLB License Master file pulled Nov 4, 202677

License numbers are the ones the utilities recorded on the interconnection applications (77 of 77 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Local solar permits naming its license

Solar permits in city and county open data that list LLUMETEC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20192020Total
unincorporated San Diego County1029503224

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Santa Clara32
Alameda18
Contra Costa11
San Mateo3
Marin2
Solano2
Sonoma2
Calaveras1
Napa1
Orange1
Placer1
San Bernardino1
San Francisco1
Shasta1

Top cities

CityInstalls
San Jose31
Oakland8
Livermore3
Fremont2
Hayward2
Walnut Creek2
American Canyon1
Anderson1
Bay Point1
Benicia1
Berkeley1
Brentwood1
Castro Valley1
Concord1
Copperopolis1

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
LLUMETEC77

Common questions

Where does LLUMETEC install solar?

Its installs are spread across 14 counties. The most are in Santa Clara County (32 installs), followed by Alameda County (18).

How often does LLUMETEC install batteries with solar?

6.5% of its interconnected solar installs include battery storage across all years.

How many LLUMETEC installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 77 interconnected installs with a tariff recorded (77) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources