Direct Energy Solar
How many solar installs has Direct Energy Solar done in California, and which license number is on its installs?
Direct Energy Solar has 205 residential solar installs interconnected in California, active in the records from 2014 through 2016 (Jun 5, 2014 to Oct 7, 2016), most of them in Orange County (46), San Diego County (42) and Los Angeles County (29). The license number recorded on most of its installs, 992952, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 205
- Last 24 months
- 0
- Total capacity
- 1,331.4 kW DC
- Median system size
- 5.7 kW DC
- With battery storage
- 0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
- Third-party owned
- 14.3% of 189 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 0 installs
- Ownership types recorded
- PPA 3, lease 24
- First install
- Jun 5, 2014
- Latest install
- Oct 7, 2016
- Counties
- 14
- Utilities
- SCE 126, SDGE 62, PGE 17
- CSLB license
- 992952
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2014 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2014 | 2 | 0 |
| 2015 | 99 | 0 |
| 2016 | 104 | 0 |
| 2017 | 0 | 0 |
| 2018 | 0 | 0 |
| 2019 | 0 | 0 |
| 2020 | 0 | 0 |
| 2021 | 0 | 0 |
| 2022 | 0 | 0 |
| 2023 | 0 | 0 |
| 2024 | 0 | 0 |
| 2025 | 0 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
None of its 205 interconnected installs with a tariff recorded (205) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 204 | 99.5% | not counted |
| NEM 2.0 | 1 | 0.5% | not recorded |
| Net Billing Tariff | 0 | 0.0% | 0 |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.
Leases, PPAs and third-party owners
On 27 of Direct Energy Solar’s installs the utility recorded a third-party ownership type: PPA 3, lease 24, prepaid lease 0, other 0. Across all installers, 8 residential systems list a third-party owner name that matches Direct Energy Solar exactly (after removing case, punctuation and suffixes such as Inc or LLC).
| Third-party owner named on its installs | Installs |
|---|---|
| Direct Energy Solar | 8 |
| Astrum Solar dba Dir | 6 |
| Kilowatt Systems, LLC | 5 |
| Jeff Flanzer | 2 |
| Kilowatt | 2 |
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
Across all years, 202 of Direct Energy Solar’s 205 installs name a module maker in the “Generator Manufacturer” fields, and most of those (152, 75.2%) used modules recorded as Kyocera.
Across all years, 205 of Direct Energy Solar’s 205 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (205, 100.0%) used inverters recorded as Enphase.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | Kyocera | 0 | 152 |
| LG | 0 | 27 | |
| Suniva | 0 | 21 | |
| Hyundai | 0 | 1 | |
| Renesola America | 0 | 1 | |
| Inverter maker | Enphase | 0 | 205 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 202 of 205 installs, inverters on 205. See the methodology and the equipment index.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 992952 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 138 | ||||
License numbers are the ones the utilities recorded on the interconnection applications (142 of 205 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
Other names reported under the same license
- Astrum Solar: 58 installs, license 992952
Counties
| County | Installs |
|---|---|
| Orange | 46 |
| San Diego | 42 |
| Los Angeles | 29 |
| Riverside | 24 |
| Ventura | 17 |
| Santa Barbara | 16 |
| San Bernardino | 10 |
| Tulare | 7 |
| Kern | 6 |
| Fresno | 4 |
| Kings | 1 |
| Madera | 1 |
| San Luis Obispo | 1 |
| Stanislaus | 1 |
Top cities
| City | Installs |
|---|---|
| San Clemente | 10 |
| San Diego | 10 |
| Santa Barbara | 8 |
| Fallbrook | 5 |
| Irvine | 5 |
| Palmdale | 5 |
| Bakersfield | 4 |
| Brea | 4 |
| Chula Vista | 4 |
| La Mesa | 4 |
| Laguna Niguel | 4 |
| Ramona | 4 |
| Ventura | 4 |
| Visalia | 4 |
| Beaumont | 3 |
Names as recorded by the utilities
The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| Direct Energy Solar | 200 |
| DIRECT ENERGY SOLAR | 3 |
| Direct energy Solar | 2 |
Common questions
Where does Direct Energy Solar install solar?
Its installs are spread across 14 counties. The most are in Orange County (46 installs), followed by San Diego County (42).
How often does Direct Energy Solar install batteries with solar?
0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.
How many Direct Energy Solar installs are under NEM 3.0 (the Net Billing Tariff)?
None of its 205 interconnected installs with a tariff recorded (205) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.