How many solar installs has Triple Line Solar done in California, and which license number is on its installs?

Triple Line Solar has 311 residential solar installs interconnected in California, active in the records from 2011 through 2023 (Jul 21, 2011 to Aug 10, 2023), most of them in Riverside County (161), San Bernardino County (72) and San Diego County (36). CSLB lists license 958524 (sole owner license, name not shown) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-46, expires Mar 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
311
Last 24 months
0
Total capacity
2,347.7 kW DC
Median system size
7 kW DC
With battery storage
0.7% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
Third-party owned
43.6% of 266 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
PPA 7, lease 109
Median battery size
6.3 kWh (2 installs list a capacity)
First install
Jul 21, 2011
Latest install
Aug 10, 2023
Counties
8
Utilities
SCE 271, SDGE 38, PGE 2
CSLB license
958524

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2011 to 2026

YearInstalls interconnectedWith battery storage
201160
2012620
2013520
2014410
2015360
2016130
2017110
2018150
2019161
2020160
2021100
2022191
2023140
202400
202500
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 311 interconnected installs with a tariff recorded (311) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.021067.5%not counted
NEM 2.010132.5%2 (2.6%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

On 116 of Triple Line Solar’s installs the utility recorded a third-party ownership type: PPA 7, lease 109, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches Triple Line Solar exactly.

Third-party owner named on its installsInstalls
Sunpower Solar Program 1, LLC55
Sunpower Capital, LLC43
SunPower Solar Program I, LLC9
Kilowatt System LLC4
Kilowatt Systems3

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 119 of Triple Line Solar’s 311 installs name a module maker in the “Generator Manufacturer” fields, and most of those (67, 56.3%) used modules recorded as Canadian Solar.

Across all years, 311 of Triple Line Solar’s 311 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (109, 35.0%) used inverters recorded as SunPower.

Across all years, 1 of Triple Line Solar’s 311 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Generac.

1 of 2 battery-paired PG&E and SCE installs (50.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerCanadian Solar067
SolarWorld018
Trina Solar018
Qcells06
Mission Solar02
Inverter makerSunPower0109
Enphase088
SMA048
SolarEdge035
ABB016
Battery makerGenerac01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 119 of 311 installs, inverters on 311. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
958524Sole owner license (name not shown)CLEARC-46 Solar ContractorMar 8, 2011Mar 31, 2027296

License numbers are the ones the utilities recorded on the interconnection applications (298 of 311 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 958524. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list Triple Line Solar’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense201920212024Total
unincorporated San Diego County9585241113

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Riverside161
San Bernardino72
San Diego36
Los Angeles25
Orange14
Humboldt1
San Luis Obispo1
Ventura1

Top cities

CityInstalls
Murrieta72
Temecula23
Alta Loma20
Rancho Cucamonga20
Corona15
San Diego13
La Verne11
Carlsbad8
Fontana8
Lake Elsinore8
Winchester8
Wildomar7
Glendora6
Hemet6
Menifee5

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Triple Line Solar211
TRIPLE LINE SOLAR100

Common questions

Where does Triple Line Solar install solar?

Its installs are spread across 8 counties. The most are in Riverside County (161 installs), followed by San Bernardino County (72).

How often does Triple Line Solar install batteries with solar?

0.7% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many Triple Line Solar installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 311 interconnected installs with a tariff recorded (311) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.