How many solar installs has PLUG IT IN SYSTEMS INC done in California, and which license number is on its installs?
PLUG IT IN SYSTEMS INC has 424 residential solar installs interconnected in California, active in the records from 2017 through 2025 (Sep 27, 2017 to Dec 12, 2025), most of them in Los Angeles County (291), Ventura County (105) and Orange County (13). CSLB lists license 986882 (PLUG IT IN SOLAR) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Sep 30, 2027.
License status changes daily. Confirm it on CSLB’s own license check before relying on it.
- Interconnected installs
- 424
- Last 24 months
- 3
- Total capacity
- 3,659.4 kW DC
- Median system size
- 7.6 kW DC
- With battery storage
- 43.9% all time; 33.3% last 24 months
- Third-party owned
- 0.0% of 424 installs where ownership was reported
- Net Billing Tariff (NEM 3.0)
- 6 installs, latest Nov 13, 2023
- Ownership types recorded
- none recorded
- Median battery size
- 27 kWh (185 installs list a capacity)
- First install
- Sep 27, 2017
- Latest install
- Dec 12, 2025
- Counties
- 7
- Utilities
- SCE 423, PGE 1
- CSLB license
- 986882
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs by year, 2017 to 2026
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2017 | 1 | 0 |
| 2018 | 1 | 0 |
| 2019 | 2 | 2 |
| 2020 | 41 | 15 |
| 2021 | 63 | 49 |
| 2022 | 136 | 61 |
| 2023 | 153 | 41 |
| 2024 | 25 | 18 |
| 2025 | 2 | 0 |
| 2026 (through Aug 31, 2026) | 0 | 0 |
Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)
6 of its 424 interconnected installs (1.4% of the 424 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Nov 13, 2023.
| Tariff recorded by the utility | Installs | Share of installs with a tariff | With battery storage |
|---|---|---|---|
| NEM 1.0 | 1 | 0.2% | not counted |
| NEM 2.0 | 417 | 98.3% | 179 (42.9%) |
| Net Billing Tariff | 6 | 1.4% | 6 (100.0%) |
The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.
Leases, PPAs and third-party owners
The utilities recorded no third-party ownership type (PPA or lease) on PLUG IT IN SYSTEMS INC’s installs. No residential system in the file lists a third-party owner name that matches PLUG IT IN SYSTEMS INC exactly.
Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.
Equipment recorded
In the last 24 months, 3 of PLUG IT IN SYSTEMS INC’s 3 installs name a module maker in the “Generator Manufacturer” fields, and most of those (2, 66.7%) used modules recorded as SunPower.
In the last 24 months, 3 of PLUG IT IN SYSTEMS INC’s 3 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (2, 66.7%) used inverters recorded as SunPower.
In the last 24 months, 1 of PLUG IT IN SYSTEMS INC’s 3 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (1, 100.0%) used batteries recorded as Tesla.
178 of 186 battery-paired PG&E and SCE installs (95.7%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.
| Equipment | Maker as recorded | Installs, last 24 months | Installs, all years |
|---|---|---|---|
| Module maker | SunPower | 2 | 189 |
| Aptos Solar | 1 | not in top list | |
| Inverter maker | SunPower | 2 | 53 |
| SolarEdge | 1 | 143 | |
| Battery maker | Tesla | 1 | 105 |
Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 410 of 424 installs, inverters on 424. See the methodology and the equipment index.
SGIP battery storage projects
The SGIP report names PLUG IT IN SYSTEMS INC as developer on 0 battery storage projects and as installer on 667 (0 name it as both), 667 projects in all with 19,207 kWh of storage. 353 have the status Paid, with $9,157,456 in current incentive allocations. Applications were received from Jun 21, 2017 to Dec 19, 2025.
By status
| Status as published | Projects | Storage kWh | Current incentive |
|---|---|---|---|
| Paid | 353 | 10,358 | $9,157,456 |
| Reserved | 7 | 198 | $125,820 |
| Cancelled | 305 | 8,630 | $8,420,590 |
| RRF Rejected | 2 | 21 | $4,027 |
By budget category
| Budget category | Projects | Storage kWh | Current incentive | Paid projects | Paid: current incentive |
|---|---|---|---|---|---|
| Equity Resiliency | 580 | 17,207 | $17,217,845 | 285 | $8,835,359 |
| Small Residential Storage | 55 | 919 | $161,573 | 48 | $140,815 |
| Large-Scale Storage | 28 | 1,004 | $276,514 | 20 | $181,282 |
| Residential Solar and Storage Equity - AB 209 Non-POU | 1 | 26 | $22,435 | 0 | $0 |
| Residential Storage Equity | 1 | 30 | $25,500 | 0 | $0 |
| Not stated | 2 | 21 | $4,027 | 0 | $0 |
Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.
A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.
Contractor license
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Issued | Expires | Installs reported |
|---|---|---|---|---|---|---|
| 986882 | PLUG IT IN SOLAR (Corporation) | CLEAR | C-10 Electrical Contractor | Sep 16, 2013 | Sep 30, 2027 | 424 |
License numbers are the ones the utilities recorded on the interconnection applications (424 of 424 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.
Disciplinary bonds and pending actions in the License Master file
The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 986882. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.
Local solar permits naming its license
Solar permits in city and county open data that list PLUG IT IN SYSTEMS INC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.
| Permit data | License | 2020 | Total |
|---|---|---|---|
| unincorporated San Diego County | 986882 | 1 | 1 |
Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.
Other names reported under the same license
- Plug It In Solar: 295 installs, license 986882
Counties
| County | Installs |
|---|---|
| Los Angeles | 291 |
| Ventura | 105 |
| Orange | 13 |
| Riverside | 7 |
| San Bernardino | 5 |
| Santa Barbara | 2 |
| San Mateo | 1 |
Top cities
| City | Installs |
|---|---|
| Simi Valley | 69 |
| Santa Clarita | 27 |
| Long Beach | 18 |
| Topanga | 14 |
| Acton | 11 |
| Santa Monica | 11 |
| Agoura Hills | 10 |
| Altadena | 10 |
| Malibu | 9 |
| Thousand Oaks | 8 |
| Bellflower | 7 |
| Canyon Country | 7 |
| Monterey Park | 7 |
| Valencia | 7 |
| Calabasas | 6 |
Names as recorded by the utilities
The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.
| Installer name as recorded | Installs |
|---|---|
| PLUG IT IN SYSTEMS INC | 424 |
Common questions
Where does PLUG IT IN SYSTEMS INC install solar?
Its installs are spread across 7 counties. The most are in Los Angeles County (291 installs), followed by Ventura County (105).
How often does PLUG IT IN SYSTEMS INC install batteries with solar?
43.9% of its interconnected solar installs include battery storage across all years, and 33.3% in the last 24 months (1 of 3).
How many PLUG IT IN SYSTEMS INC installs are under NEM 3.0 (the Net Billing Tariff)?
6 of its 424 interconnected installs (1.4% of the 424 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
- Self-Generation Incentive Program (SGIP) program administrators: Real-Time Public Report of SGIP applications (selfgenca.com)
Records last pulled Nov 16, 2026. Every entry links to the original public record.