SOLAR SPECTROM INC has 44 residential solar installs interconnected in California, active in the records from 2018 through 2026 (Oct 5, 2018 to May 18, 2026), most of them in Ventura County (28), Los Angeles County (10) and Orange County (4). CSLB lists license 1040428 (SOLAR SPECTROM INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-46, expires Jun 30, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
44
Last 24 months
6
Total capacity
481 kW DC
Median system size
8.1 kW DC
With battery storage
53.5% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; 66.7% of PG&E and SCE installs (SDG&E does not record storage on the solar record) last 24 months
Third-party owned
0.0% of 44 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
5 installs, latest May 2, 2025
Ownership types recorded
none recorded
Median battery size
40.8 kWh (23 installs list a capacity)
First install
Oct 5, 2018
Latest install
May 18, 2026
Counties
5
Utilities
SCE 43, SDGE 1
CSLB license
1040428

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2018 to 2026

YearInstalls interconnectedWith battery storage
201810
201900
202022
202100
2022144
20231710
202463
202533
2026 (through Aug 31, 2026)11

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

5 of its 44 interconnected installs (11.4% of the 44 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 40.0% of those include battery storage. The latest Net Billing Tariff install was approved May 2, 2025.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.03988.6%21 (55.3%)
Net Billing Tariff511.4%2 (40.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on SOLAR SPECTROM INC’s installs. No residential system in the file lists a third-party owner name that matches SOLAR SPECTROM INC exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 6 of SOLAR SPECTROM INC’s 6 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (2, 33.3%) used modules recorded as Qcells.

In the last 24 months, 6 of SOLAR SPECTROM INC’s 6 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (5, 83.3%) used inverters recorded as Enphase.

In the last 24 months, 3 of SOLAR SPECTROM INC’s 6 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (3, 100.0%) used batteries recorded as FranklinWH.

18 of 23 battery-paired PG&E and SCE installs (78.3%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells28
United Renewable Energy218
Axitec14
Enphase1not in top list
REC12
Inverter makerEnphase522
SolarEdge117
Battery makerFranklinWH33

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 37 of 44 installs, inverters on 44. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names SOLAR SPECTROM INC as developer on 32 battery storage projects and as installer on 29 (29 name it as both), 32 projects in all with 992 kWh of storage. 23 have the status Paid, with $674,595 in current incentive allocations. Applications were received from Jun 7, 2020 to Apr 6, 2026.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid23741$674,595
Reserved141$40,800
Waitlist119$28,764
Cancelled7191$220,008

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency26888$917,40818$656,600
Small Residential Storage446$8,2894$8,289
Large-Scale Storage139$9,7061$9,706
Residential Solar and Storage Equity - AB 209 Non-POU119$28,7640$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1040428SOLAR SPECTROM INC (Corporation)CLEARC-46 Solar ContractorJun 8, 2018Jun 30, 202844

License numbers are the ones the utilities recorded on the interconnection applications (44 of 44 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1040428. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
Ventura28
Los Angeles10
Orange4
Riverside1
San Diego1

Top cities

CityInstalls
Moorpark16
Calabasas3
Simi Valley3
Arcadia2
La Crescenta2
Newbury Park2
Oak Park2
Santa Rosa Valley2
Bell Canyon1
Camarillo1
Cypress1
Eastvale1
Fullerton1
Hidden Hills1
Monrovia1

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SOLAR SPECTROM INC43
Solar Spectrom1

Common questions

Where does SOLAR SPECTROM INC install solar?

Its installs are spread across 5 counties. The most are in Ventura County (28 installs), followed by Los Angeles County (10).

How often does SOLAR SPECTROM INC install batteries with solar?

53.5% of its interconnected solar installs include battery storage across all years, and 66.7% in the last 24 months (4 of 6). Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many SOLAR SPECTROM INC installs are under NEM 3.0 (the Net Billing Tariff)?

5 of its 44 interconnected installs (11.4% of the 44 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 40.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.