Solar Crew

How many solar installs has Solar Crew done in California, and which license number is on its installs?

Solar Crew has 44 residential solar installs interconnected in California, active in the records from 2013 through 2019 (Jul 8, 2013 to Oct 2, 2019), most of them in San Bernardino County (26), Riverside County (8) and Orange County (4). CSLB lists license 931995 (ROOMS COVERS N SOLAR) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, D-03, expires Jan 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
44
Last 24 months
0
Total capacity
292.7 kW DC
Median system size
6.4 kW DC
With battery storage
0.0% of PG&E and SCE installs (SDG&E does not record storage on the solar record) all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 36 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
First install
Jul 8, 2013
Latest install
Oct 2, 2019
Counties
5
Utilities
SCE 39, SDGE 5
CSLB license
931995

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2013 to 2026

YearInstalls interconnectedWith battery storage
201310
201420
2015180
2016140
201780
201800
201910
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

The battery column counts PG&E and SCE records only. SDG&E files a battery as its own project record, so its solar records never show storage.

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 44 interconnected installs with a tariff recorded (44) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.03988.6%not counted
NEM 2.0511.4%not recorded
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves. Battery shares use PG&E and SCE installs only: SDG&E files a battery as its own project record, not on the solar record, so its solar records never show storage.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Solar Crew’s installs. No residential system in the file lists a third-party owner name that matches Solar Crew exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 36 of Solar Crew’s 44 installs name a module maker in the “Generator Manufacturer” fields, and most of those (26, 72.2%) used modules recorded as Axitec.

Across all years, 44 of Solar Crew’s 44 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (37, 84.1%) used inverters recorded as APsystems (Altenergy Power System).

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerAxitec026
Silfab04
Astronergy (Chint)03
LG01
Qcells01
Inverter makerAPsystems (Altenergy Power System)037
Enphase06
SMA01

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 36 of 44 installs, inverters on 44. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
931995ROOMS COVERS N SOLAR (Corporation)CLEARC-10 Electrical Contractor; D-03Apr 29, 2009Jan 31, 202744

License numbers are the ones the utilities recorded on the interconnection applications (44 of 44 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 931995. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Other names reported under the same license

Counties

CountyInstalls
San Bernardino26
Riverside8
Orange4
Los Angeles3
San Diego3

Top cities

CityInstalls
Rancho Cucamonga7
Upland5
Alta Loma4
Corona3
Fontana2
Rialto2
Riverside2
Canyon Lake1
Chino1
Claremont1
Colton1
Eastvale1
El Cajon1
Fountain Valley1
Hemet1

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Solar Crew35
SOLAR CREW8
Solar crew1

Common questions

Where does Solar Crew install solar?

Its installs are spread across 5 counties. The most are in San Bernardino County (26 installs), followed by Riverside County (8).

How often does Solar Crew install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years. Shares use PG&E and SCE installs only, because SDG&E files batteries as separate project records.

How many Solar Crew installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 44 interconnected installs with a tariff recorded (44) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.