Mid Matthews Construction

How many solar installs has Mid Matthews Construction done in California, and which license number is on its installs?

Mid Matthews Construction has 219 residential solar installs interconnected in California, active in the records from 2017 through 2026 (Jul 14, 2017 to Jun 8, 2026), most of them in Calaveras County (106), Tuolumne County (29) and San Joaquin County (27). CSLB lists license 866078 (sole owner license, name not shown) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, expires Aug 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
219
Last 24 months
20
Total capacity
2,407.1 kW DC
Median system size
8.6 kW DC
With battery storage
11.4% all time; 75.0% last 24 months
Third-party owned
0.0% of 219 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
22 installs, latest Jun 8, 2026
Ownership types recorded
none recorded
Median battery size
27 kWh (9 installs list a capacity)
First install
Jul 14, 2017
Latest install
Jun 8, 2026
Counties
16
Utilities
PGE 218, SCE 1
CSLB license
866078

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2017 to 2026

YearInstalls interconnectedWith battery storage
201730
2018190
2019390
2020290
2021431
2022291
2023292
2024127
20251210
2026 (through Aug 31, 2026)44

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

22 of its 219 interconnected installs (10.0% of the 219 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Jun 8, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.020.9%not counted
NEM 2.019589.0%3 (1.5%)
Net Billing Tariff2210.0%22 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Mid Matthews Construction’s installs. No residential system in the file lists a third-party owner name that matches Mid Matthews Construction exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 20 of Mid Matthews Construction’s 20 installs name a module maker in the “Generator Manufacturer” fields, and most of those (13, 65.0%) used modules recorded as Qcells.

In the last 24 months, 20 of Mid Matthews Construction’s 20 installs name an inverter maker in the “Inverter Manufacturer” fields, and the most common maker (9, 45.0%) used inverters recorded as Enphase.

In the last 24 months, 15 of Mid Matthews Construction’s 20 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (9, 60.0%) used batteries recorded as Tesla.

25 of 25 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells13137
Canadian Solar535
JA Solar1not in top list
JinkoSolar19
REC1not in top list
Inverter makerEnphase9138
Tesla99
PointGuard Energy Inc.22
Battery makerTesla99
Enphase412
PointGuard Energy Inc.22

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 218 of 219 installs, inverters on 219. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Mid Matthews Construction as developer on 14 battery storage projects and as installer on 13 (13 name it as both), 14 projects in all with 969 kWh of storage. 4 have the status Paid, with $63,340 in current incentive allocations. Applications were received from Apr 16, 2024 to Nov 26, 2025.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid4110$63,340
Reserved3209$125,880
Cancelled7650$428,302

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency6576$463,0772$56,400
Large-Scale Storage4157$25,0510$0
Small Residential Storage376$10,9632$6,940
Non-Residential Storage Equity1160$118,4310$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
866078Sole owner license (name not shown)CLEARB General Building ContractorOct 18, 2005Aug 31, 2028219

License numbers are the ones the utilities recorded on the interconnection applications (219 of 219 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 866078. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
Calaveras106
Tuolumne29
San Joaquin27
Contra Costa20
Alameda12
Placer5
Santa Clara4
Solano4
San Mateo3
Amador2
El Dorado2
Kings1
Mariposa1
Monterey1
San Benito1
Stanislaus1

Top cities

CityInstalls
Copperopolis70
Sonora19
Manteca13
Angels Camp10
Stockton7
Murphys6
Brentwood5
San Andreas5
Jamestown4
Rocklin4
Valley Springs4
Antioch3
Danville3
Dublin3
Escalon3

Names as recorded by the utilities

The utilities recorded this installer under 2 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
MID MATTHEWS CONSTRUCTION168
Mid Matthews Construction51

Common questions

Where does Mid Matthews Construction install solar?

Its installs are spread across 16 counties. The most are in Calaveras County (106 installs), followed by Tuolumne County (29).

How often does Mid Matthews Construction install batteries with solar?

11.4% of its interconnected solar installs include battery storage across all years, and 75.0% in the last 24 months (15 of 20).

How many Mid Matthews Construction installs are under NEM 3.0 (the Net Billing Tariff)?

22 of its 219 interconnected installs (10.0% of the 219 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.