GKRW LLC

How many solar installs has GKRW LLC done in California, and which license number is on its installs?

GKRW LLC has 66 residential solar installs interconnected in California, active in the records from 2016 through 2021 (Jun 17, 2016 to Nov 20, 2021), most of them in Orange County (54), Riverside County (7) and San Bernardino County (3). CSLB lists license 999669 (ECOFORCE SOLUTIONS) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, expires Jan 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
66
Last 24 months
0
Total capacity
722.6 kW DC
Median system size
10 kW DC
With battery storage
7.6% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 66 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
Median battery size
19.6 kWh (5 installs list a capacity)
First install
Jun 17, 2016
Latest install
Nov 20, 2021
Counties
4
Utilities
SCE 66
CSLB license
999669

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2016 to 2026

YearInstalls interconnectedWith battery storage
201610
201770
2018110
2019141
2020241
202193
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 66 interconnected installs with a tariff recorded (66) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.023.0%not counted
NEM 2.06497.0%4 (6.3%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on GKRW LLC’s installs. No residential system in the file lists a third-party owner name that matches GKRW LLC exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 66 of GKRW LLC’s 66 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (30, 45.5%) used modules recorded as Solaria.

Across all years, 66 of GKRW LLC’s 66 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (62, 93.9%) used inverters recorded as SolarEdge.

Across all years, 5 of GKRW LLC’s 66 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (5, 100.0%) used batteries recorded as LG.

5 of 5 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSolaria030
LG021
SolarWorld08
Qcells04
Hyundai02
Inverter makerSolarEdge062
SMA02
Enphase01
SunPower01
Battery makerLG05

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 66 of 66 installs, inverters on 66. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names GKRW LLC as developer on 39 battery storage projects and as installer on 37 (37 name it as both), 39 projects in all with 1,099 kWh of storage. 27 have the status Paid, with $157,925 in current incentive allocations. Applications were received from Jun 19, 2020 to Mar 21, 2025.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid27417$157,925
PBI in Process2485$102,665
Reserved110$9,603
Cancelled7158$58,476
RRF Rejected229$4,352

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage24315$47,07619$35,825
Equity Resiliency7149$143,3855$95,370
Large-Scale Storage6606$138,2093$26,730
Not stated229$4,3520$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
999669ECOFORCE SOLUTIONS (Limited Liability)CLEARB General Building ContractorJan 2, 2015Jan 31, 202766

License numbers are the ones the utilities recorded on the interconnection applications (66 of 66 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 999669. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list GKRW LLC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense20182019Total
unincorporated San Diego County999669213

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Orange54
Riverside7
San Bernardino3
Los Angeles2

Top cities

CityInstalls
Trabuco Canyon21
Coto de Caza9
Corona2
Cypress2
Huntington Beach2
Laguna Beach2
Lake Forest2
Mission Viejo2
Palm Springs2
Rancho Santa Margarita2
Villa Park2
Aliso Viejo1
Artesia1
Chino1
Chino Hills1

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
GKRW LLC61
GKRW LLC dba EcoForce Solutions4
GKRW LLC DBA ECOFORCE SOLUTIONS1

Common questions

Where does GKRW LLC install solar?

Its installs are spread across 4 counties. The most are in Orange County (54 installs), followed by Riverside County (7).

How often does GKRW LLC install batteries with solar?

7.6% of its interconnected solar installs include battery storage across all years.

How many GKRW LLC installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 66 interconnected installs with a tariff recorded (66) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.