Free Energy Systems

How many solar installs has Free Energy Systems done in California, and which license number is on its installs?

Free Energy Systems has 283 residential solar installs interconnected in California, active in the records from 2013 through 2020 (Jul 3, 2013 to Feb 18, 2020), most of them in Santa Clara County (79), Alameda County (50) and San Mateo County (49). The license number recorded on most of its installs, 988918, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
283
Last 24 months
0
Total capacity
1,319.3 kW DC
Median system size
4.3 kW DC
With battery storage
0.0% all time; no installs in the last 24 months last 24 months
Third-party owned
2.5% of 283 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
lease 7
First install
Jul 3, 2013
Latest install
Feb 18, 2020
Counties
15
Utilities
PGE 281, SCE 2
CSLB license
988918

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2013 to 2026

YearInstalls interconnectedWith battery storage
201330
2014570
20151000
20161210
201700
201800
201910
202010
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 283 interconnected installs with a tariff recorded (283) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.028199.3%not counted
NEM 2.020.7%0 (0.0%)
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 7 of Free Energy Systems’s installs the utility recorded a third-party ownership type: PPA 0, lease 7, prepaid lease 0, other 0. No residential system in the file lists a third-party owner name that matches Free Energy Systems exactly.

Third-party owner named on its installsInstalls
Varney Johnson6
Sunnova Corporation1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 277 of Free Energy Systems’ 283 installs name a module maker in the “Generator Manufacturer” fields, and most of those (226, 81.6%) used modules recorded as SolarWorld.

Across all years, 283 of Free Energy Systems’ 283 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (157, 55.5%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSolarWorld0226
Canadian Solar021
Silfab021
LG03
Panasonic02
Inverter makerEnphase0157
APsystems (Altenergy Power System)0107
ABB07
Power-One07
SolarEdge04

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 277 of 283 installs, inverters on 283. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Free Energy Systems as developer on 2 battery storage projects and as installer on 0 (0 name it as both), 2 projects in all with 32 kWh of storage. 1 have the status Paid, with $16,160 in current incentive allocations. Applications were received from Dec 23, 2020 to Aug 18, 2021.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid116$16,160
Cancelled116$2,593

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Equity Resiliency116$16,1601$16,160
Small Residential Storage116$2,5930$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
988918Not found in the CSLB License Master file pulled Nov 4, 2026263

License numbers are the ones the utilities recorded on the interconnection applications (264 of 283 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Local solar permits naming its license

Solar permits in city and county open data that list Free Energy Systems’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense201820192020Total
City and County of San Francisco9889181102
unincorporated Marin County9889180213

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Santa Clara79
Alameda50
San Mateo49
Contra Costa36
San Francisco21
Sonoma12
Santa Cruz9
Fresno8
Solano5
Marin4
San Joaquin3
Los Angeles2
Monterey2
Napa2
Lake1

Top cities

CityInstalls
San Jose51
San Francisco21
Daly City11
Hayward10
South San Francisco10
Concord8
Fremont7
Pacifica7
East Palo Alto6
Oakland6
Union City6
Antioch5
San Leandro5
San Mateo5
Campbell4

Names as recorded by the utilities

The utilities recorded this installer under 5 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Free Energy Systems232
free energy systems47
FREE ENERGY SYSTEMS INC2
Free energy systems1
FREE ENERGY SYSTEMS1

Common questions

Where does Free Energy Systems install solar?

Its installs are spread across 15 counties. The most are in Santa Clara County (79 installs), followed by Alameda County (50).

How often does Free Energy Systems install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years.

How many Free Energy Systems installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 283 interconnected installs with a tariff recorded (283) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.