CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION

How many solar installs has CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION done in California, and which license number is on its installs?

CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION has 70 residential solar installs interconnected in California, active in the records from 2021 through 2026 (Sep 14, 2021 to Jun 19, 2026), most of them in Los Angeles County (34), San Bernardino County (14) and Orange County (8). CSLB lists license 1074466 (CURRENT CONSTRUCTION) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, expires Apr 30, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
70
Last 24 months
61
Total capacity
596.8 kW DC
Median system size
8 kW DC
With battery storage
84.3% all time; 95.1% last 24 months
Third-party owned
75.7% of 70 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
61 installs, latest Jun 19, 2026
Ownership types recorded
PPA 33, lease 1, other 19
Median battery size
13.5 kWh (59 installs list a capacity)
First install
Sep 14, 2021
Latest install
Jun 19, 2026
Counties
7
Utilities
SCE 70
CSLB license
1074466

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2021 to 2026

YearInstalls interconnectedWith battery storage
202110
202231
202300
202450
20255756
2026 (through Aug 31, 2026)42

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

61 of its 70 interconnected installs (87.1% of the 70 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 95.1% of those include battery storage. The latest Net Billing Tariff install was approved Jun 19, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.0912.9%1 (11.1%)
Net Billing Tariff6187.1%58 (95.1%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 53 of CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION’s installs the utility recorded a third-party ownership type: PPA 33, lease 1, prepaid lease 0, other 19. Across all installers, 3 residential systems list a third-party owner name that matches CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Lightreach32
GoodLeap17
Mosaic2
GoodLeap TPO1
GoodLeapLTPO1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 61 of CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION’s 61 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (29, 47.5%) used modules recorded as LONGi.

In the last 24 months, 61 of CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION’s 61 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (34, 55.7%) used inverters recorded as SolarEdge.

In the last 24 months, 57 of CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION’s 61 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (33, 57.9%) used batteries recorded as SolarEdge.

58 of 59 battery-paired PG&E and SCE installs (98.3%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerLONGi2929
JA Solar2828
Solaria26
Canadian Solar14
Qcells13
Inverter makerSolarEdge3435
Tesla2626
Enphase29
Battery makerSolarEdge3333
Tesla2424

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 70 of 70 installs, inverters on 70. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION as developer on 32 battery storage projects and as installer on 33 (32 name it as both), 33 projects in all with 458 kWh of storage. 0 have the status Paid, with $0 in current incentive allocations. Applications were received from Dec 11, 2023 to Jul 2, 2025.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Reserved113$18,246
Cancelled32445$773,692

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Residential Solar and Storage Equity - AB 209 Non-POU31433$774,1040$0
Residential Solar and Storage Equity - AB 209 POU113$16,1170$0
Small Residential Storage111$1,7160$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1074466CURRENT CONSTRUCTION (Limited Liability)CLEARB General Building ContractorApr 2, 2021Apr 30, 202770

License numbers are the ones the utilities recorded on the interconnection applications (70 of 70 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1074466. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
Los Angeles34
San Bernardino14
Orange8
Riverside8
Ventura3
Kings2
Kern1

Top cities

CityInstalls
Chino4
Alta Loma3
Corona3
Long Beach3
Valencia3
Covina2
Downey2
Garden Grove2
Hanford2
Los Angeles2
Newhall2
Norco2
Palmdale2
West Covina2
Westminster2

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION70

Common questions

Where does CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION install solar?

Its installs are spread across 7 counties. The most are in Los Angeles County (34 installs), followed by San Bernardino County (14).

How often does CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION install batteries with solar?

84.3% of its interconnected solar installs include battery storage across all years, and 95.1% in the last 24 months (58 of 61).

How many CURRENT ENERGY LLC DBA CURRENT CONSTRUCTION installs are under NEM 3.0 (the Net Billing Tariff)?

61 of its 70 interconnected installs (87.1% of the 70 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 95.1% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.