A Plus Solar Solutions

How many solar installs has A Plus Solar Solutions done in California, and which license number is on its installs?

A Plus Solar Solutions has 36 residential solar installs interconnected in California, active in the records from 2015 through 2017 (Sep 2, 2015 to Feb 15, 2017), most of them in Riverside County (12), Los Angeles County (11) and Orange County (7). CSLB lists license 763154 (A PLUS HEATING & AIR CONDITIONING CO) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications B, C-10, C-20, C-36, expires May 31, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
36
Last 24 months
0
Total capacity
215.8 kW DC
Median system size
5.9 kW DC
With battery storage
0.0% all time; no installs in the last 24 months last 24 months
Third-party owned
0.0% of 36 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
0 installs
Ownership types recorded
none recorded
First install
Sep 2, 2015
Latest install
Feb 15, 2017
Counties
4
Utilities
SCE 36
CSLB license
763154

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2015 to 2026

YearInstalls interconnectedWith battery storage
2015170
2016160
201730
201800
201900
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)00

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

None of its 36 interconnected installs with a tariff recorded (36) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.036100.0%not counted
NEM 2.000.0%0
Net Billing Tariff00.0%0

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on A Plus Solar Solutions’s installs. No residential system in the file lists a third-party owner name that matches A Plus Solar Solutions exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

Across all years, 36 of A Plus Solar Solutions’ 36 installs name a module maker in the “Generator Manufacturer” fields, and most of those (36, 100.0%) used modules recorded as SolarWorld.

Across all years, 36 of A Plus Solar Solutions’ 36 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (36, 100.0%) used inverters recorded as Enphase.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerSolarWorld036
Inverter makerEnphase036

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 36 of 36 installs, inverters on 36. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
763154A PLUS HEATING & AIR CONDITIONING CO (Corporation)CLEARB General Building Contractor; C-10 Electrical Contractor; C-20 Warm-Air Heating, Ventilating and Air-Conditioning Contractor; C-36May 18, 1999May 31, 202734

License numbers are the ones the utilities recorded on the interconnection applications (36 of 36 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 763154. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
Riverside12
Los Angeles11
Orange7
San Bernardino6

Top cities

CityInstalls
Whittier3
Highland2
Murrieta2
Perris2
Yorba Linda2
Azusa1
Beaumont1
Chino1
Chino Hills1
Compton1
Corona1
Covina1
Diamond Bar1
Fontana1
La Palma1

Names as recorded by the utilities

The utilities recorded this installer under 4 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
A Plus Solar Solutions33
a Plus Solar solutions1
A Plus solar Solutions1
A Plus Solar solutions1

Common questions

Where does A Plus Solar Solutions install solar?

Its installs are spread across 4 counties. The most are in Riverside County (12 installs), followed by Los Angeles County (11).

How often does A Plus Solar Solutions install batteries with solar?

0.0% of its interconnected solar installs include battery storage across all years.

How many A Plus Solar Solutions installs are under NEM 3.0 (the Net Billing Tariff)?

None of its 36 interconnected installs with a tariff recorded (36) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.