Home solar in ZIP code 95991, California
Service city recorded on most installs: Yuba City. County: Sutter County.
How many homes in ZIP code 95991 have solar?
PG&E, SCE and SDG&E interconnected 3,424 residential solar systems in ZIP code 95991 through Aug 31, 2026, 349 of them in the last 24 months (Sep 2024 through Aug 2026). The utilities recorded Yuba City, Sutter County, as the service city on 3,424 of them. Westhaven Inc has the most installs recorded in this ZIP, 481.
Counts of interconnected systems from utility records, not a rating of any installer.
Data: California DG Stats interconnection records (Interconnected_Project_Sites_2026-08-31.zip), which run through Aug 31, 2026. ZIP codes are the service ZIP the utility recorded on each project.
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
At a glance
- Residential solar installs
- 3,424
- Last 24 months
- 349 (Sep 2024 through Aug 2026)
- Capacity
- 25.7 MW DC
- Median system size
- 7 kW DC
- Net Billing Tariff (NEM 3.0)
- 474 installs, 13.8% of those with a tariff recorded
- Utility
- PGE 3,424
- First install in data
- Nov 14, 2001
- Latest install in data
- Aug 31, 2026
Installs by year
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2001 | 1 | 0 |
| 2002 | 1 | 0 |
| 2003 | 2 | 0 |
| 2004 | 1 | 0 |
| 2005 | 2 | 0 |
| 2006 | 1 | 0 |
| 2007 | 8 | 0 |
| 2008 | 2 | 0 |
| 2009 | 3 | 0 |
| 2010 | 12 | 0 |
| 2011 | 12 | 0 |
| 2012 | 23 | 0 |
| 2013 | 44 | 0 |
| 2014 | 146 | 0 |
| 2015 | 299 | 0 |
| 2016 | 259 | 0 |
| 2017 | 202 | 0 |
| 2018 | 234 | 1 |
| 2019 | 305 | 3 |
| 2020 | 258 | 11 |
| 2021 | 281 | 12 |
| 2022 | 425 | 21 |
| 2023 | 417 | 45 |
| 2024 | 196 | 157 |
| 2025 | 182 | 152 |
| 2026 (through Aug 31, 2026) | 108 | 78 |
Battery storage
14.0% of the residential solar installs here include battery storage across all years (480 of 3,424). In the last 24 months the share was 81.4% (284 of 349).
Net metering tariff
Of the 3,424 installs with a net metering tariff recorded: NEM 1.0 832 (24.3%), NEM 2.0 2,118 (61.9%), the Net Billing Tariff (often called NEM 3.0) 474 (13.8%). The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023, under CPUC Decision D.22-12-056.
Lease, PPA or owned
30.0% of the 3,424 installs with ownership recorded are third-party owned (a lease or power purchase agreement); the other 2,396 are recorded as not third-party owned. Ownership types recorded: PPA 862, lease 119, prepaid lease 3, other 44.
Installers by installs in 95991
Installers with a page in this index, most installs in this ZIP first. 258 such installers have at least one install here. 57 more installs were by 47 installer names without a page in this index. 68 were self-installed or had no installer recorded. Counts of connected systems, not a rating.
| Installer | Installs in 95991 | Last 24 months |
|---|---|---|
| Westhaven Inc | 481 | 29 |
| Tesla Energy Operations (formerly SolarCity) | 283 | 6 |
| Sunrun | 262 | 77 |
| Vivint Solar Developer, LLC | 182 | 0 |
| Infinity Energy, Inc | 160 | 2 |
| V3 Electric | 155 | 8 |
| Bright Planet Solar | 136 | 0 |
| FREEDOM FOREVER LLC | 81 | 10 |
| Sunworks | 55 | 0 |
| Gold Rush Energy Solutions | 49 | 0 |
City and county recorded for 95991
The Service City and Service County the utilities entered on this ZIP’s installs, as recorded. No outside ZIP directory is used.
| Recorded as | Installs |
|---|---|
| City: Yuba City | 3,424 |
| County: Sutter County | 3,424 |
Common questions
How common are home batteries with solar in 95991?
14.0% of the residential solar installs here include battery storage across all years (480 of 3,424). In the last 24 months the share was 81.4% (284 of 349).
How many solar installs in 95991 are under NEM 3.0?
474 of the 3,424 installs here with a tariff recorded (13.8%) were interconnected under the Net Billing Tariff, often called NEM 3.0, which applies to interconnection applications submitted on or after April 15, 2023.
Which solar installers have the most installs in 95991?
Among installers with a page in this index, by installs interconnected here through Aug 31, 2026: Westhaven Inc (481), Tesla Energy Operations (formerly SolarCity) (283), Sunrun (262). These are counts of connected systems, not a rating of price, workmanship or service.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- California Public Utilities Commission: NEM Revisit proceeding R.20-08-020 and Decision D.22-12-056
Records last pulled Nov 16, 2026. Every entry links to the original public record.