How many solar installs has Sbrega Electric done in California, and which license number is on its installs?

Sbrega Electric has 169 residential solar installs interconnected in California, active in the records from 2018 through 2026 (Apr 5, 2018 to Jul 20, 2026), most of them in Madera County (106), Mariposa County (39) and Fresno County (23). CSLB lists license 1034923 (SBREGA ELECTRIC INC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Mar 31, 2028.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
169
Last 24 months
42
Total capacity
1,492.2 kW DC
Median system size
8.3 kW DC
With battery storage
56.2% all time; 95.2% last 24 months
Third-party owned
0.0% of 169 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
38 installs, latest Jul 20, 2026
Ownership types recorded
none recorded
Median battery size
15 kWh (78 installs list a capacity)
First install
Apr 5, 2018
Latest install
Jul 20, 2026
Counties
4
Utilities
PGE 169
CSLB license
1034923

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2018 to 2026

YearInstalls interconnectedWith battery storage
201880
2019154
2020158
2021199
20222516
20233412
20241813
20252424
2026 (through Aug 31, 2026)119

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

38 of its 169 interconnected installs (22.5% of the 169 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Jul 20, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.031.8%not counted
NEM 2.012875.7%54 (42.2%)
Net Billing Tariff3822.5%38 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on Sbrega Electric’s installs. No residential system in the file lists a third-party owner name that matches Sbrega Electric exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 42 of Sbrega Electric’s 42 installs name a module maker in the “Generator Manufacturer” fields, and most of those (31, 73.8%) used modules recorded as REC.

In the last 24 months, 42 of Sbrega Electric’s 42 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (24, 57.1%) used inverters recorded as Tesla.

In the last 24 months, 23 of Sbrega Electric’s 42 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (21, 91.3%) used batteries recorded as Tesla.

44 of 95 battery-paired PG&E and SCE installs (46.3%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerREC3153
Briggs & Stratton, LLC10not in top list
CertainTeed4not in top list
Aptos Solar2not in top list
Discover Energy Systems Corp.2not in top list
Inverter makerTesla2424
Sol-Ark1754
Enphase452
SMA2not in top list
SolarEdge236
Battery makerTesla2121
Enphase13
Lithion Battery Inc.1not in top list

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 156 of 169 installs, inverters on 169. See the methodology and the equipment index.

SGIP battery storage projects

The SGIP report names Sbrega Electric as developer on 15 battery storage projects and as installer on 15 (15 name it as both), 15 projects in all with 277 kWh of storage. 12 have the status Paid, with $103,892 in current incentive allocations. Applications were received from Jul 9, 2018 to Jun 13, 2025.

By status

Status as publishedProjectsStorage kWhCurrent incentive
Paid12178$103,892
Reserved164$64,172
Pending Reservation113$28,469
Cancelled122$22,002

By budget category

Budget categoryProjectsStorage kWhCurrent incentivePaid projectsPaid: current incentive
Small Residential Storage891$19,9708$19,970
Equity Resiliency6173$170,0964$83,922
Residential Solar and Storage Equity - AB 209 Non-POU113$28,4690$0

Each project is one SGIP application with the equipment type Electrochemical Storage in the program administrators’ Real-Time Public Report, downloaded Nov 16, 2026. Incentive amounts are its Current Incentive field, which the SGIP report defines as “The latest and most current incentive allocation.” For the Residential Solar and Storage Equity categories that amount includes the solar incentive. Status is the Budget Classification field (“Payment status based on the application's fully qualified state.”), or the Fully Qualified State where it is blank. Amounts are as published, not payments verified by this site.

A project counts here when its Developer Company Name or Installer Name, normalized the same way as the utilities’ installer names, equals this installer’s name or one of the spellings combined on this page. The SGIP report has no license number, so no license join is made. See all SGIP battery projects and the methodology.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
1034923SBREGA ELECTRIC INC (Corporation)CLEARC-10 Electrical ContractorJan 17, 2018Mar 31, 2028168

License numbers are the ones the utilities recorded on the interconnection applications (169 of 169 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 1034923. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Counties

CountyInstalls
Madera106
Mariposa39
Fresno23
Solano1

Top cities

CityInstalls
Coarsegold60
Mariposa31
Oakhurst25
Fresno9
Clovis7
Midpines5
Ahwahnee4
Madera4
North Fork4
Raymond3
Yosemite National Park3
Bass Lake2
Friant2
Prather2
Auberry1

Names as recorded by the utilities

The utilities recorded this installer under 3 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
SBREGA ELECTRIC INC138
Sbrega Electric22
SBREGA ELECTRIC9

Common questions

Where does Sbrega Electric install solar?

Its installs are spread across 4 counties. The most are in Madera County (106 installs), followed by Mariposa County (39).

How often does Sbrega Electric install batteries with solar?

56.2% of its interconnected solar installs include battery storage across all years, and 95.2% in the last 24 months (40 of 42).

How many Sbrega Electric installs are under NEM 3.0 (the Net Billing Tariff)?

38 of its 169 interconnected installs (22.5% of the 169 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.