KAAR ELECTRIC

How many solar installs has KAAR ELECTRIC done in California, and which license number is on its installs?

KAAR ELECTRIC has 149 residential solar installs interconnected in California, active in the records from 2021 through 2026 (Feb 3, 2021 to Jun 16, 2026), most of them in Los Angeles County (105), Ventura County (32) and Orange County (6). CSLB lists license 873768 (KAAR ELECTRIC) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, expires Apr 30, 2027.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
149
Last 24 months
20
Total capacity
1,163.3 kW DC
Median system size
7 kW DC
With battery storage
14.1% all time; 40.0% last 24 months
Third-party owned
0.0% of 149 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
24 installs, latest Jun 16, 2026
Ownership types recorded
none recorded
Median battery size
10 kWh (21 installs list a capacity)
First install
Feb 3, 2021
Latest install
Jun 16, 2026
Counties
5
Utilities
SCE 149
CSLB license
873768

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2021 to 2026

YearInstalls interconnectedWith battery storage
2021526
2022273
2023423
2024121
202593
2026 (through Aug 31, 2026)75

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

24 of its 149 interconnected installs (16.1% of the 149 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 37.5% of those include battery storage. The latest Net Billing Tariff install was approved Jun 16, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.000.0%not counted
NEM 2.012583.9%12 (9.6%)
Net Billing Tariff2416.1%9 (37.5%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

The utilities recorded no third-party ownership type (PPA or lease) on KAAR ELECTRIC’s installs. No residential system in the file lists a third-party owner name that matches KAAR ELECTRIC exactly.

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 20 of KAAR ELECTRIC’s 20 installs name a module maker in the “Generator Manufacturer” fields, and the most common maker (10, 50.0%) used modules recorded as REC.

In the last 24 months, 20 of KAAR ELECTRIC’s 20 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (20, 100.0%) used inverters recorded as Enphase.

In the last 24 months, 8 of KAAR ELECTRIC’s 20 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (8, 100.0%) used batteries recorded as Enphase.

19 of 21 battery-paired PG&E and SCE installs (90.5%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerREC1034
United Renewable Energy529
Hyundai3not in top list
Qcells230
Inverter makerEnphase2075
Battery makerEnphase813

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 145 of 149 installs, inverters on 149. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
873768KAAR ELECTRIC (Corporation)CLEARC-10 Electrical ContractorMar 3, 2006Apr 30, 2027149

License numbers are the ones the utilities recorded on the interconnection applications (149 of 149 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. Check the current record at CSLB.

Disciplinary bonds and pending actions in the License Master file

The CSLB License Master file pulled Nov 4, 2026 lists no disciplinary bond, pending suspension date or pending classification removal date for license 873768. The file does not list citations, accusations or complaints, which appear only on CSLB’s license detail page.

Local solar permits naming its license

Solar permits in city and county open data that list KAAR ELECTRIC’s primary license number, the one the utilities recorded on the most of its installs. Matched by CSLB license number only, never by name. A license can be shared by several names in this index, so the count is for the license, not only this name. A permit is not an install: one home can have more than one permit, and a permit does not show the system was finished or connected.

Permit dataLicense2020Total
unincorporated San Diego County87376811

Of the permit portals this index reads, only these publish the contractor’s license number: City and County of San Francisco, unincorporated San Diego County and unincorporated Marin County. Permits elsewhere are not linked to installers. Checked Nov 16, 2026.

Other names reported under the same license

Counties

CountyInstalls
Los Angeles105
Ventura32
Orange6
Riverside3
San Bernardino3

Top cities

CityInstalls
Simi Valley17
Santa Monica8
Rancho Palos Verdes5
Valencia5
Camarillo4
Newbury Park4
Sierra Madre4
Torrance4
Agoura Hills3
Alhambra3
Baldwin Park3
Glendora3
La Canada3
Long Beach3
Monrovia3

Names as recorded by the utilities

The utilities recorded this installer under 1 spelling. See the methodology for how spellings are combined.

Installer name as recordedInstalls
KAAR ELECTRIC149

Common questions

Where does KAAR ELECTRIC install solar?

Its installs are spread across 5 counties. The most are in Los Angeles County (105 installs), followed by Ventura County (32).

How often does KAAR ELECTRIC install batteries with solar?

14.1% of its interconnected solar installs include battery storage across all years, and 40.0% in the last 24 months (8 of 20).

How many KAAR ELECTRIC installs are under NEM 3.0 (the Net Billing Tariff)?

24 of its 149 interconnected installs (16.1% of the 149 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 37.5% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.