Prime Solar Co.

How many solar installs has Prime Solar Co. done in California, and which license number is on its installs?

Prime Solar Co. has 39 residential solar installs interconnected in California, active in the records from 2002 through 2026 (Jul 18, 2002 to Aug 14, 2026), most of them in Ventura County (30), Santa Barbara County (3) and Los Angeles County (2). The license number recorded on most of its installs, 457857, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

License status changes daily. Confirm it on CSLB’s own license check before relying on it.

Interconnected installs
39
Last 24 months
5
Total capacity
246.2 kW DC
Median system size
4.9 kW DC
With battery storage
12.8% all time; 100.0% last 24 months
Third-party owned
4.5% of 22 installs where ownership was reported
Net Billing Tariff (NEM 3.0)
5 installs, latest Aug 14, 2026
Ownership types recorded
other 1
Median battery size
13.5 kWh (5 installs list a capacity)
First install
Jul 18, 2002
Latest install
Aug 14, 2026
Counties
7
Utilities
SCE 37, PGE 2
CSLB license
457857

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs by year, 2002 to 2026

YearInstalls interconnectedWith battery storage
200220
200310
200450
200510
200650
200720
200800
200940
201050
201120
201200
201310
201420
201530
201600
201700
201800
201910
202000
202100
202200
202300
202400
202500
2026 (through Aug 31, 2026)55

Net metering tariff: NEM 1.0, NEM 2.0 and the Net Billing Tariff (NEM 3.0)

5 of its 39 interconnected installs (12.8% of the 39 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The latest Net Billing Tariff install was approved Aug 14, 2026.

Tariff recorded by the utilityInstallsShare of installs with a tariffWith battery storage
NEM 1.03384.6%not counted
NEM 2.012.6%0 (0.0%)
Net Billing Tariff512.8%5 (100.0%)

The tariff is the NEM Tariff field on each DG Stats record. The CPUC’s Decision D.22-12-056 set the Net Billing Tariff for customers who submit an interconnection application on or after April 15, 2023 (CPUC), so installs approved before mid 2023 are almost all NEM 1.0 or NEM 2.0. A count of tariffs is not a measure of what a system saves.

Leases, PPAs and third-party owners

On 1 of Prime Solar Co.’s installs the utility recorded a third-party ownership type: PPA 0, lease 0, prepaid lease 0, other 1. Across all installers, 1 residential systems list a third-party owner name that matches Prime Solar Co. exactly (after removing case, punctuation and suffixes such as Inc or LLC).

Third-party owner named on its installsInstalls
Prime Solar Co.1

Owner names are written as the utilities recorded them, matched only on exact spelling after that clean-up, so one company can appear under more than one name. The record shows who was named as owner when the system was connected; it does not show later sales of a contract or a portfolio.

Equipment recorded

In the last 24 months, 5 of Prime Solar Co.’s 5 installs name a module maker in the “Generator Manufacturer” fields, and most of those (5, 100.0%) used modules recorded as Qcells.

In the last 24 months, 5 of Prime Solar Co.’s 5 installs name an inverter maker in the “Inverter Manufacturer” fields, and most of those (3, 60.0%) used inverters recorded as Tesla.

In the last 24 months, 5 of Prime Solar Co.’s 5 installs name a battery maker in the “Generator Manufacturer” fields, and most of those (3, 60.0%) used batteries recorded as Tesla.

5 of 5 battery-paired PG&E and SCE installs (100.0%) name a battery maker in the Generator fields. SDG&E files a battery as its own project record, so SDG&E solar records name modules and inverters only.

EquipmentMaker as recordedInstalls, last 24 monthsInstalls, all years
Module makerQcells55
Inverter makerTesla3not in top list
SolarEdge23
Enphase112
Battery makerTesla33
Enphase11
SolarEdge11

Counts are installs that name the maker at least once, not panel or inverter quantities. Modules and batteries are read from “Generator Manufacturer 1” to “Generator Manufacturer 7”; inverters from “Inverter Manufacturer 1” to “Inverter Manufacturer 26”. Installs with these fields blank, or naming no maker (for example “UNKNOWN”), are not counted: modules are named on 9 of 39 installs, inverters on 39. See the methodology and the equipment index.

Contractor license

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsIssuedExpiresInstalls reported
457857Not found in the CSLB License Master file pulled Nov 4, 202634

License numbers are the ones the utilities recorded on the interconnection applications (39 of 39 installs carry one). Numbers seen on fewer than 1% of an installer’s installs are treated as typos and not looked up. CSLB’s License Master lists active licenses and expired licenses that can still be renewed; cancelled and revoked licenses, and licenses expired more than five years, are not in it. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Counties

CountyInstalls
Ventura30
Santa Barbara3
Los Angeles2
Kern1
Merced1
Orange1
Tuolumne1

Top cities

CityInstalls
Ojai14
Camarillo8
Ventura4
Oak View3
Santa Barbara2
Carpinteria1
Frazier Park1
Fullerton1
Hacienda Heights1
La Grange1
Livingston1
Palmdale1
Somis1

Names as recorded by the utilities

The utilities recorded this installer under 6 spellings. See the methodology for how spellings are combined.

Installer name as recordedInstalls
Prime Solar Co.25
PRIME SOLAR CO6
PRIME SOLAR LLC5
Prime Solar1
prime solar co1
Prime Solar Co1

Common questions

Where does Prime Solar Co. install solar?

Its installs are spread across 7 counties. The most are in Ventura County (30 installs), followed by Santa Barbara County (3).

How often does Prime Solar Co. install batteries with solar?

12.8% of its interconnected solar installs include battery storage across all years, and 100.0% in the last 24 months (5 of 5).

How many Prime Solar Co. installs are under NEM 3.0 (the Net Billing Tariff)?

5 of its 39 interconnected installs (12.8% of the 39 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 100.0% of those include battery storage. The Net Billing Tariff applies to interconnection applications submitted on or after April 15, 2023.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. A status such as a bond or insurance suspension is CSLB’s record at that time, not a finding by this site, and statuses change daily. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.