The most recent install credited to SunPower in California’s interconnection data was approved in August 2026; it has 2,144 in the last 12 complete months (September 2025 through August 2026). CSLB lists license 961988 (SUNPOWER) with status CLEAR in the License Master file pulled Nov 4, 2026, classifications C-10, C-46, expires Oct 31, 2027, the number recorded on 1,656 of those installs.
The interconnection record shows installs the utilities approved to connect to the grid under an installer name. It cannot show whether a company is still in business, has been sold or has filed for bankruptcy.
The installs credited to SunPower in the last 12 complete months carry more than one CSLB license number: 961988 on 1,656 (CSLB holder SUNPOWER, Orem) and 890895 on 487 (not found in the CSLB License Master file), in the License Master file pulled Nov 4, 2026. They are grouped under one installer by the name written on the applications; the records do not say whether these numbers belong to the same legal entity.
- Latest install approved
- Aug 31, 2026
- Last 12 complete months
- 2,144 installs, September 2025 through August 2026
- Last 24 months
- 7,474 installs
- All time
- 119,561 installs, first approved Jul 23, 2007
- License on most recent installs
- 961988, SUNPOWER, CSLB status CLEAR in the License Master file pulled Nov 4, 2026
- Full record
- SunPower installer page
Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.
Installs in each of the last 12 complete months
| Month approved | Installs credited to SunPower |
|---|---|
| August 2026 | 127 |
| July 2026 | 119 |
| June 2026 | 154 |
| May 2026 | 139 |
| April 2026 | 259 |
| March 2026 | 219 |
| February 2026 | 268 |
| January 2026 | 173 |
| December 2025 | 281 |
| November 2025 | 139 |
| October 2025 | 172 |
| September 2025 | 94 |
| Total | 2,144 |
Net Billing Tariff installs
7,634 of the installs credited to SunPower (6.4% of the 119,561 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and 39.5% of those on PG&E and SCE records include battery storage. The latest was approved Aug 31, 2026.
Systems that list SunPower as third-party owner
Leased and PPA systems carry a Third Party Name on the interconnection record, whoever installed them. These owner names contain “sunpower” as a whole word. They are listed separately because the record does not say whether two spellings are the same legal entity.
| Third-party owner as recorded | Residential systems |
|---|---|
| SunPower | 19,019 |
| SunPower Capital, LLC | 6,650 |
| SunPower Solar Program 1, LLC | 660 |
| SunPower Solar Program I, LLC | 490 |
| SunPower SolarProgram I, LLC | 302 |
From the 200 most common owner names in the DG Stats file current through Aug 31, 2026. The record does not show later transfers of a contract or portfolio, and it does not show what happens to a lease or PPA.
Installs by year
| Year | Installs interconnected | With battery storage |
|---|---|---|
| 2007 | 82 | 0 |
| 2008 | 479 | 0 |
| 2009 | 490 | 0 |
| 2010 | 504 | 0 |
| 2011 | 637 | 0 |
| 2012 | 1,501 | 0 |
| 2013 | 2,483 | 0 |
| 2014 | 1,933 | 1 |
| 2015 | 1,941 | 0 |
| 2016 | 2,503 | 0 |
| 2017 | 3,570 | 2 |
| 2018 | 6,749 | 1 |
| 2019 | 7,006 | 1 |
| 2020 | 9,953 | 12 |
| 2021 | 15,029 | 517 |
| 2022 | 21,762 | 1,218 |
| 2023 | 23,377 | 1,954 |
| 2024 | 14,637 | 2,471 |
| 2025 | 3,467 | 349 |
| 2026 (through Aug 31, 2026) | 1,458 | 259 |
License numbers on installs in the last 12 months
| License | CSLB business name | CSLB status, file pulled Nov 4, 2026 | Classifications | Expires | Installs |
|---|---|---|---|---|---|
| 961988 | SUNPOWER | CLEAR, Pending Case/CIT | C-10 Electrical Contractor; C-46 Solar Contractor | Oct 31, 2027 | 1,656 |
| 890895 | Not found in the CSLB License Master file pulled Nov 4, 2026 | 487 | |||
Names written on these installs: SUNPOWER (1,094), SunPower Corporation (451), SUNPOWER CORPORATION SYSTEMS (409), SunPower (190). 2,144 of the 2,144 carry a CSLB number. Numbers on fewer than 3 installs or 1% of them are left out as likely typos. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.
Other installer names in the records
Installer names that share a license number with SunPower, or contain the same brand word. A shared word or number does not by itself mean the same company.
| Installer | Why listed | Latest install | Last 12 months | All time |
|---|---|---|---|---|
| Complete Solar | same license 961988 | August 2026 | 738 | 13,319 |
| SUNPOWER BY SEA BRIGHT SOLAR | name contains “sunpower” | August 2026 | 80 | 2,760 |
| Sol Nova LLC | same license 961988 | October 2025 | 3 | 592 |
| SunPower Corporation - Merideth | name contains “sunpower” | September 2013 | 0 | 532 |
| Complete Solar Solution of California In | same license 961988 | November 2016 | 0 | 304 |
| SUNPOWER CORP, SYSTEM INTEGRATOR | same license 890895; name contains “sunpower” | August 2015 | 0 | 86 |
| COMPLETE SOLAR SOLUTION OF CALIFORNIA INC | same license 961988 | March 2018 | 0 | 68 |
How to read this record
Each install is a home solar system that Pacific Gas and Electric, Southern California Edison or San Diego Gas & Electric approved to connect to the grid. The month is the App Approved date, which comes after the system is installed. The installer is the name written on the interconnection application. Counts run through Aug 31, 2026, the latest date in the DG Stats file Interconnected_Project_Sites_2026-08-31.zip.
To check a license today, use CSLB’s license check. See every installer’s latest install and the large installers with no installs in the last six months.
Common questions
When was the last install credited to SunPower approved?
The latest App Approved date on an install credited to SunPower is Aug 31, 2026, in the DG Stats file current through Aug 31, 2026. Its first was Jul 23, 2007.
How many solar installs has SunPower had in California in the last 12 months?
2,144 residential solar installs credited to SunPower were approved for interconnection from September 2025 through August 2026. Across all years it has 119,561.
How many California solar systems list SunPower as the third-party owner?
In the DG Stats file current through Aug 31, 2026, 19,019 residential systems list “SunPower” and 6,650 residential systems list “SunPower Capital, LLC” and 660 residential systems list “SunPower Solar Program 1, LLC” and 490 residential systems list “SunPower Solar Program I, LLC” and 302 residential systems list “SunPower SolarProgram I, LLC” as the third-party owner (lease or PPA), counted separately because the spellings differ. The record shows the owner named when each system was connected. It does not show what happens to a lease or PPA contract; those terms are in the contract itself.
Does a recent install mean SunPower is still in business?
No. The interconnection record shows installs the utilities approved to connect to the grid under an installer name. It cannot show whether a company is still in business, has been sold or has filed for bankruptcy. An installer name can stay on applications filed before a change, and a business can work under a new name or license.
Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. Neither record states whether a company is in business. Confirm any license directly with CSLB. Report an error or add a company response.
Sources
- California Distributed Generation Statistics: Interconnected Project Sites Data Set (PG&E, SCE, SDG&E)
- Contractors State License Board: Master List of California Licensed Contractors
Records last pulled Nov 16, 2026. Every entry links to the original public record.