The most recent install credited to Lennar in California’s interconnection data was approved in July 2026; it has 68 in the last 12 complete months (September 2025 through August 2026). The license number recorded on most of those installs, 1003498, was not found in the CSLB License Master file pulled Nov 4, 2026. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

The interconnection record shows installs the utilities approved to connect to the grid under an installer name. It cannot show whether a company is still in business, has been sold or has filed for bankruptcy.

Latest install approved
Jul 24, 2026
Last 12 complete months
68 installs, September 2025 through August 2026
Last 24 months
1,201 installs
All time
5,333 installs, first approved Mar 20, 2014
License on most recent installs
1003498, not found in the CSLB License Master file pulled Nov 4, 2026
Full record
Lennar installer page

Counts cover homes served by Pacific Gas and Electric, Southern California Edison and San Diego Gas & Electric, the three utilities that report to California DG Stats. Homes served by municipal utilities such as LADWP (City of Los Angeles) and SMUD (Sacramento) are not in this data. See the methodology.

Installs in each of the last 12 complete months

Month approvedInstalls credited to Lennar
August 20260
July 20262
June 20261
May 20260
April 20260
March 20264
February 20262
January 20260
December 202536
November 20256
October 20254
September 202513
Total68

Net Billing Tariff installs

1,168 of the installs credited to Lennar (21.9% of the 5,333 with a tariff recorded) were interconnected under the Net Billing Tariff, the successor to NEM 2.0 often called NEM 3.0, and battery storage is not recorded on those SDG&E solar records. The latest was approved Jul 24, 2026.

Installs by year

YearInstalls interconnectedWith battery storage
2014320
2015300
2016130
2017400
2018580
20192790
20207070
20217990
20227540
20239540
20249310
20257270
2026 (through Aug 31, 2026)90

License numbers on installs in the last 12 months

LicenseCSLB business nameCSLB status, file pulled Nov 4, 2026ClassificationsExpiresInstalls
1003498Not found in the CSLB License Master file pulled Nov 4, 202666

Names written on these installs: Lennar (68). 68 of the 68 carry a CSLB number. Numbers on fewer than 3 installs or 1% of them are left out as likely typos. The file was searched by license number only. That is not a finding about the contractor beyond that search: the file leaves out cancelled, revoked and long-expired licenses, and a number in the utilities’ data can be mistyped.

Other installer names in the records

Installer names that share a license number with Lennar, or contain the same brand word. A shared word or number does not by itself mean the same company.

InstallerWhy listedLatest installLast 12 monthsAll time
SUNNOVA ENERGY CORPORATIONsame license 1003498August 20267516,057
SunStreet Energy Group LLCsame license 1001133August 2023011,878
Lennar Homes/Sunstreet Energysame license 1001133December 201601,513
Momentum Solarsame license 1003498November 202511,011
Lennar Homessame license 1001133March 20180617
SunStreet Energy Group/Lennarsame license 1001133December 20150180
SunStreet Energy Group/Lennar Homessame license 1001133January 20170175
SUNSTREET ENERGYsame license 1001133July 2015059

How to read this record

Each install is a home solar system that Pacific Gas and Electric, Southern California Edison or San Diego Gas & Electric approved to connect to the grid. The month is the App Approved date, which comes after the system is installed. The installer is the name written on the interconnection application. Counts run through Aug 31, 2026, the latest date in the DG Stats file Interconnected_Project_Sites_2026-08-31.zip.

To check a license today, use CSLB’s license check. See every installer’s latest install and the large installers with no installs in the last six months.

Common questions

When was the last install credited to Lennar approved?

The latest App Approved date on an install credited to Lennar is Jul 24, 2026, in the DG Stats file current through Aug 31, 2026. Its first was Mar 20, 2014.

How many solar installs has Lennar had in California in the last 12 months?

68 residential solar installs credited to Lennar were approved for interconnection from September 2025 through August 2026. Months with none recorded: January 2026, April 2026, May 2026 and August 2026. Across all years it has 5,333.

Does a recent install mean Lennar is still in business?

No. The interconnection record shows installs the utilities approved to connect to the grid under an installer name. It cannot show whether a company is still in business, has been sold or has filed for bankruptcy. An installer name can stay on applications filed before a change, and a business can work under a new name or license.

Install counts are the utilities’ interconnection records as published by California DG Stats, current through Aug 31, 2026. License facts are copied from CSLB’s License Master file pulled Nov 4, 2026. Neither record states whether a company is in business. Confirm any license directly with CSLB. Report an error or add a company response.

Sources

Records last pulled Nov 16, 2026. Every entry links to the original public record.